scrum - How to handle unplanned items in JIRA/Greenhopper -


i have setup jira , greenhopper , set initial sprint. have done scrum during years via whiteboard , face-to-face communication. wonder how should handle unplanned items using greenhopper? don't want add new card , have screw statistics. nice able figure of ammount of unplanned work when sprint done. initial guess add new card on task board , tag unplanned. don't seem find unplanned tag card.

i've been using greenhopper 1 1/2 years. works pretty , invaluable our team isn't substitute post-its on daily stand-up. on 1.5 years, we've ended collecting lot of tasks, bugs, , other items in jira aren't immediate backlog items. managing them difficult in greenhopper. these unscheduled items.

i have these versions set in greenhopper:

unscheduled: holding pen few hundred items may or may not ever around to. ideas, bugs can't fix @ moment.

unscrubbed bugs: find new bugs aren't related current sprint's work, go in here. every week or so, go through them , place them in 1 of other versions.

short term roadmap: stuff we'll not in or next sprint.

sprint planning: backlog work during planning. it's higher priority items.

v2.3 - sprint 2 (or whatever version/sprint working): sprint backlog.

during current sprint , before our sprint planning session, organize backlog , place high priority items in sprint planning them next. after meeting, place items sign todo v2.3 - sprint 2 , them manage on daily basis.